prelanding Planning as of 2014-06-19T15-56-45
- [2014-03-17T00:00 - 2014-04-07T00:00] MTP_001: NCD (Near Comet Drift, 5.35-1.9 MKm) - PL Commissioning: graphs and 3d
- [2014-04-07T00:00 - 2014-05-07T12:48] MTP_002: NCD (Near Comet Drift, 5.35-1.9 MKm) - PL Commissioning: graphs and 3d
- [2014-05-07T12:48 - 2014-06-04T10:50] MTP_003: NCD (Near Comet Drift, 1.9 MKm - 465000 Km): graphs and 3d
- [2014-06-04T10:50 - 2014-07-02T08:35] MTP_004: NCD (465000 Km - 50000 Km): graphs and 3d
- [2014-07-02T08:35 - 2014-08-01T10:00] MTP_005: FAT (Far Approach Trajectory, 50000 Km - 380 Km): graphs and 3d
- [2014-08-01T10:00 - 2014-09-02T10:00] MTP_006: Comet Characterisation: graphs and 3d
- [2014-09-02T10:00 - 2014-09-23T10:00] MTP_007: Transition to GMP and first part of GMP (Global Mapping Phase): graphs and 3d
- [2014-09-23T10:00 - 2014-10-24T10:00] MTP_008: Global Mapping Phase (cont.) and COP (Close Observation Phase): graphs and 3d
- [2014-10-24T10:00 - 2014-11-19T02:00] MTP_009: Landing preparation, landing and FSS(First Science Sequence): graphs and 3d